Sample 7+7 Risk Assessment Matrix...


Risk Rating = Frequency (Likelihood) ranking + Consequence ranking

 

It is very important to note however, that adding the frequency and consequence rankings only works if the changes in both the frequency and consequence estimates (as represented by the changes in their corresponding ranking numbers) are separated by the same factor.

 

This solution works for any factor difference (two, five, ten, one hundred, etc.) providing both the frequency and consequence ranking estimates are separated by the same factor.

 

Sample 7+7 Risk Assessment Matrix

Events with the potential for significantly different outcomes

 

When assigning frequency and consequence rankings to hazardous events the rankings are based normally on the average frequency of occurrence and the average consequences for the event. For some hazardous events, however, different outcomes can lead to significantly different consequences. For example, a train derailment would typically only lead to minor injuries, due perhaps to passengers falling over inside the train, whereas in extreme cases, derailments can lead to multiple fatalities. It is recommended that in such cases, to get a better understanding of the risk profile, particularly in relation to potential multi-fatality outcomes, two separate rankings should be considered for the hazardous event as follows:

 

a) the first ranking should relate to the frequency and consequences of the typical (most frequent outcome),

 

and

 

b) the second risk ranking should relate to the frequency and consequences of the realistic worst case outcome, if appropriate.